Free change order template
Copy it, print it, or get it signed by text. No email required.
A change order is a written agreement to add work, cost, or time to a contract you have already signed. To be worth anything later it needs five things: what changed, what it costs, what the new total becomes, the date, and both signatures. The template below has all five.
The template
CHANGE ORDER Contractor: ____________________________ Phone: ______________ Customer: ______________________________ Phone: ______________ Job address: ___________________________________________________ Change order number: ______ Date: ______________ Original contract amount: $______________ What is being added or changed: ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ Cost of this change: $______________ New contract total: $______________ Change to the schedule: ______ extra days, or none Both parties agree that the work described above is added to the contract, and that the contract total becomes the new total shown above. Customer signature: ____________________ Date: ____________ Contractor signature: __________________ Date: ____________
The same thing, filled in
CHANGE ORDER Contractor: Hill Renovations Phone: (307) 218 5580 Customer: Maria Alvarez Phone: (347) 555 0142 Job address: 145 Court Street, Brooklyn NY Change order number: 001 Date: September 16, 2026 Original contract amount: $18,000 What is being added or changed: Quartz countertop on the island, replacing the laminate in the original scope. Includes template, fabrication and install. Cost of this change: $2,400 New contract total: $20,400 Change to the schedule: 3 extra days Both parties agree that the work described above is added to the contract, and that the contract total becomes the new total shown above. Customer signature: Maria Alvarez Date: Sept 16, 2026 Contractor signature: Dave Hill Date: Sept 16, 2026
What every change order needs
- 1
What changed, in plain words. Write what a stranger would need to picture the work. "Quartz countertop on the island" beats "countertop upgrade".
- 2
What it costs. One number for this change, on its own.
- 3
What the total becomes. This is the number people argue about later, so put it in writing rather than making anyone do the arithmetic.
- 4
The date. Before the work starts, not after.
- 5
Both signatures. Yours and the person who pays. A verbal yes is not a signature, and neither is a name typed into an email.
Where contractors lose the money
- Doing the work first. Once it is built, you are negotiating instead of invoicing.
- Getting a yes from the wrong person. The person who says "sure, go ahead" is not always the person who signs the cheque.
- Leaving out the new total. "Plus $2,400" invites an argument. "$20,400" does not.
- No date. A change order without a date is hard to place in the story of the job, and the story is what decides who is right.
Questions contractors ask
- Does a change order have to be in writing?
- Most residential contracts require changes to be in writing, and many state contractor laws do too. Even where a verbal change is technically enforceable, proving what was agreed is the hard part, which is why written and signed is the practical standard.
- Does it have to be signed by the customer?
- Yes, in practice. An unsigned change order is a record of what you intended to charge, not evidence that anyone agreed to it.
- Can I charge for extra work without a change order?
- You can invoice for it, and you may well be owed it. Collecting it is the problem. Without something signed, it becomes your word against theirs.
- My customer agreed by text message. Is that enough?
- It is better than nothing and it has helped contractors in small claims court. It is weaker than a signed change order, because a text rarely states the new contract total and is easy to argue was about something else.
- Do I need a lawyer to write a change order?
- Not for a normal residential job. A change order is a short written amendment to a contract that already exists. For unusual work, large sums or a dispute already under way, talk to one.
- How many change orders is too many?
- There is no limit. A job with six documented changes is in better shape than a job with one undocumented one.
This template and these answers are general information, not legal advice. Contract and home improvement rules vary by state and sometimes by city. If real money is at stake, have a lawyer in your state look at your contract.
The template works. The typing is what kills it.
Every contractor already knows they should write it down. Almost nobody does, and it is not laziness. It is that you are standing in a kitchen with dust on your hands and the customer is asking for one more thing, and filling in a form is the last thing that is going to happen in that moment.
ScopeSign does the same five fields from your phone in about a minute, and your customer signs it by text before you pick the tools back up. No app for them, no login.
See how it worksWant the Word and Google Docs versions?
The template above is yours to copy for free. Leave an email and we will send the editable files.